Late payment in construction in Cameroon
By Noé Mbwang · Published on
In construction, money gets stuck in three places: progress statements waiting for approval, retention money nobody remembers to claim, and extra work done without a written order. A signed monthly statement, a release date recorded for each retention and no extra work without a priced written order solve most of it.
Where the money gets stuck
- Progress statements waiting weeks for approval. Until it is signed, the statement cannot be invoiced, and the payment clock does not start.
- Retention money, forgotten and never claimed. It is released months after the site closes, when the team is already elsewhere.
- Extra work done without a written order or amendment. When payment falls due, the client disputes it, and you have nothing to prove it.
The clauses that matter
- A signed monthly statement from the project owner or their representative, with an approval deadline written in the contract.
- The release date of each retention, entered in the tracker, with a reminder on that date.
- No extra work without a written, priced order. One line in the contract is enough: any extra work requires a signed written order before it starts.
- Proof of delivery: a signed acceptance report, with a deadline for written reservations.
The payment-terms template offers this wording, to adapt and have reviewed.
Worked example
Fictional example. A finishing-works company invoices 12,000,000 FCFA of progress statements per month. Its statements wait 20 days on average before approval, then are paid at 45 days: the money arrives 65 days after the work. If a 5-day approval deadline is written in the contract and respected, it gains 15 days, i.e. 12,000,000 ÷ 30 × 15 = 6,000,000 FCFA of cash freed.
On a 40,000,000 FCFA contract with 5% retention, 2,000,000 FCFA wait for final acceptance. A date in the tracker stops them from being forgotten.
General information, not legal advice. Any court procedure is handled by a lawyer or a bailiff.